The project's tower crane will arrive on 7/16. The installation will take two days to complete - one to erect and the second for load testing. We will let you know one week prior concerning traffic control. 

 

As of 6/23/18, we reached the bottom of the hole! With lagging complete, we'll continue to excavate dirt while we dig for our elevator pit, sand/oil separator and tower crane footings. 

 

On 6/27/18, you may have noticed a concrete truck on 165th! We are pouring a 3" rat slab in three locations required for our footings and waterproofing. It's our first pour of the project!

 

For Core 83 residents, you'll be happy to know that the temporary generator will be gone by end of July! Thank you for your cooperation and understanding. 

 

 