Piles Complete!

May 24, 2018

As of Friday, May 18th, all 129 piles have been installed! We'll continue with lagging, excavating and complete the installation of dewatering wells. 

 

166th utility work will be complete by next week, providing both lanes again to drive on. 165th will be the access point of the job, so fencing with green screen will be visible, and deliveries will occur throughout the course of the project.

 

Compass will not be working Memorial Day.

 

 