Construction Update!

August 24, 2018

As of Friday (8/24/18), we have poured the first lift of concrete for East Post-Tension concrete slab!

Below is the snapshot of cables and rebar being placed prior to the pour. 

 

Looking ahead, we plan to pour concrete for the second lift of East PT deck on Wednesday (29/8). The concrete pumping activities will be utilizing only one lane of the 166th street from approximately 11AM (PST) to 3PM (PST), while the other lane will remain open for traffic. There will be one traffic controller present on 166th during this time period to facilitate a smooth traffic flow from & around the jobsite.

 

Stay tuned for the updates!

We thank you for your continued cooperation and understanding! :) 

 