Prior to the Tower Crane Arrival
The project's tower crane will arrive on 7/16. The installation will take two days to complete - one to erect and the second for load testing. We will let you know one week prior concerning traffic control. As of 6/23/18, we reached the bottom of the hole! With lagging complete, we'll continue to excavate dirt while we dig for our elevator pit, sand/oil separator and tower crane footings. On 6/27/18, you may have noticed a concrete truck on 165th! We are pouring a 3" rat slab