October 8, 2018

A snap from top of our tower crane as we mark the end of summer!

Back-fill on the west side is currently scheduled for 10/8. The Telebelt machine will be utilizing only one lane of the 165th street from approximately 8AM to 5PM, while the other lane will remain open to...

September 24, 2018

Below is the snapshot of shotcrete being carried out on the West side as per our update from last week.

Framing hold downs and plumbing fixtures are being currently placed on the East side as seen below.

Ramp pour on the west side is currently scheduled for 9/27. The pou...

September 14, 2018

As of Friday (9/14), we have completed the concrete pour for West P1 PT deck!

Typical traffic control measures across 165th were as seen in the below image.

 Our men in action on the day of pour!

Shotcrete on the south side is currently scheduled for 9/19 & 9/21. The shot...

September 6, 2018

As of Wednesday (9/6/18), we are getting ready for P1-West PT deck concrete pouring scheduled for Thursday (9/13) and have already completed the pour for P1-East!

Concrete pumping activities on Thursday (9/13) will be utilizing only one lane of the 165th Street from app...

August 24, 2018

As of Friday (8/24/18), we have poured the first lift of concrete for East Post-Tension concrete slab!

Below is the snapshot of cables and rebar being placed prior to the pour. 

Looking ahead, we plan to pour concrete for the second lift of East PT deck on Wedn...

August 17, 2018

As per below images, we are getting ready for the East Post-Tension concrete slab to be poured on Friday 8/24!

 We have added an extra layer of protection in case of a rainfall.

Stay tuned for the updates!

We thank you for your continued cooperation and understanding! :) 

August 10, 2018

As of August 10th, we have completed the concrete pouring for the foundation mat slab.

The shotcreting for perimeter walls is underway and we expect it to be completed within the next week!

We are looking ahead for our East-PT deck to be poured on August 27th.

Stay tuned...

July 13, 2018

The tower crane erection is scheduled for Monday (7/16) followed by load testing on Tuesday (7/17).

The erection activities will be utilizing only one lane of the 165th street from 7AM (PST) to 7PM (PST), while the other lane will remain open for traffic. There will be...

July 6, 2018

As of this week,

The crane base section and embeds are here!

The steel reinforcement for crane footings, elevator pit and sand/oil separator were placed followed by concrete pouring. You may have noticed the concrete pump extending towards the middle of the site from 165...

June 27, 2018

The project's tower crane will arrive on 7/16. The installation will take two days to complete - one to erect and the second for load testing. We will let you know one week prior concerning traffic control. 

As of 6/23/18, we reached the bottom of the hole! With lagging...

Please reload