January 10, 2020

Asphalt pavement replacement is tentatively scheduled for the 14th and 15th of January 2020. Remove of existing asphalt pavement surface takes place on 1/10/20.

TRAFFIC: During the asphalt removal and replacement, the alley will be closed.

Weather conditions may affect t...

April 30, 2019

Stream Dexios' tower crane will be dismantled on Saturday 5/4/19. The crew will be on site at about 5 AM.

TRAFFIC: During the dismantle, we will maintain one-lane traffic control with periodic street closures. There will be no parking 3 AM to Midnight on Dexter between...

February 12, 2019

This month, concrete pours will pick up steam as we work our way out of the hole. Expect dirt and concrete trucks entering and exiting the site from 200th St SW.

December 4, 2018

Monday 12/10, We will pour our fourth PT deck! 

TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and bike lane will be closed on the East side of Dexter Ave. Please watch out for our flaggers as they guide traffic to allow c...

November 8, 2018

Monday 11/12, We will pour our third PT deck! 

TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and bike lane will be closed on the East side of Dexter Ave. Please watch out for our flaggers as they guide traffic to allow co...

October 18, 2018

Monday 10/22, We will pour our Second PT deck! 

TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and bike lane will be closed on the East side of Dexter Ave. Please watch out for our flaggers as they guide traffic to allow c...