Located in the Westlake neighborhood of Seattle, Stream Dexios will be a mix of apartment and retail spaces; 79 apartment units, 1 live/work unit, 3 commercial use spaces, and parking for 51 vehicles. The project will also feature private courtyards, a rooftop terrace, and street-level landscaping improvements.  Opening Spring of 2020!

We're thrilled you’re here—we have so much to share with you about the progress of our project Stream Dexios, currently under construction in your neighborhood. We'll post information regarding major events during the life of the project. Visit us often!

Construction Updates

October 18, 2018

Monday 10/22, We will pour our Second PT deck! 

TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and bike lane will be closed on the East side of Dexter Ave. Please watch out for our flaggers as they guide traffic to allow concrete trucks to access site. 

NOISE : The crew will start setting the concrete pumps at 5 AM and the pour will start at 6 AM. Noise to be ex...

September 12, 2018

Friday 10/14, We will pour our first PT deck! 

TRAFFIC: There will be continuous concrete truck traffic on Dexter Ave. The sidewalk and bike lane will be closed on the East side of Dexter Ave. Please watch out for our flaggers as they guide traffic to allow concrete trucks to access site. 

NOISE : The crew will start setting the concrete pumps at 5 AM and the pour will start at 6 AM. Noise to be exp...

July 3, 2018

Stream Dexios' tower crane will be erected on Saturday 7/7. The crew will be on site about 5 AM with crane delivery and installation to follow. Load testing will complete on Monday 7/9.

TRAFFIC: During the installation on 7/7, we will maintain one-lane traffic control with periodic street closures. There will be no parking 5 AM and 3 PM on Dexter between Galer St and Hayes St.  The traffic control will be supplied by Seattle To...

May 4, 2018

Demolition of the existing structure at 1600-1612 Dexter Avenue N is in progress and expected to take approximately 3-weeks to complete.

During this time, the east alley will be intermittently closed to support demo activities. Tenants requiring access during these closures shall enter and exit the alley through the North.  Compass will work diligently to minimize disruptions to regular traffic.

Please reload

Work Hours

Weekdays: 7:00am - 6:00pm

Saturdays: 9:00am - 6:00pm

Contact

1600 Dexter Ave N. Seattle, WA. 98109

Project Manager:

Ania Pastuszewska, ania.pastuszewska@compass-gc.com

Superintendent:

Howard Lasater, howard.lasater@compass-gc.com